Late payment statistics: how long big UK firms take to pay
Every large UK company has to publish how fast it pays its suppliers. We read all 5,623 of their reports for the first half of 2026: how long the typical one takes, how many invoices it pays late, who holds back retentions, and whether any of it is getting better.
On Google Play now. Coming soon to iPhone. Have the app? Open it
How long do big UK companies take to pay an invoice?
About a month. Across the 5,623 large UK companies that reported for periods ending in the first half of 2026, the typical one took 31 days on average to pay a supplier’s invoice, and paid 64% of its invoices within 30 days.
Those are the companies’ own figures. Every company over the size limit has to publish how it paid its suppliers, every six months, and the government keeps all of the reports in one public register. We downloaded every one of them, 115,384 reports going back to 2017, on 8 October 2026.
“The typical company” here is the median: half did better and half did worse. The plain average across all of them is 34.5 days, pulled up by a long tail of slow payers.
30 days or less on averageMore than 30 days
Share of 5,623 large UK companies by the average time to pay they reported. Source: the government’s payment practices register.
Just over half, 52%, took longer than 30 days on average, and 48% took 30 days or less. 8% took longer than 60 days, which is as long as agreed terms between businesses usually run.
- Companies in the figures
- 5,623
- Typical average time to pay
- 31 days
- Typical share paid within 30 days
- 64%
- Typical share paid after 60 days
- 5%
- Companies averaging over 30 days
- 52%
- Companies averaging over 60 days
- 8%
Medians of each company’s own reported figures, for its latest period ending between 1 January 2026 and 30 June 2026.
How many invoices do big companies pay late?
The typical big company paid 15% of its invoices later than the terms it had agreed, roughly one invoice in 7. And 12% of companies paid half or more of their invoices late.
“Late” is measured against the company’s own terms: an invoice is late if it was paid after the date the agreed terms set. That makes it a fair measure of whether a company keeps its word, and a poor measure of how long you wait.
An invoice paid on day 55 of 60 day terms counts as paid on time.
So a supplier on long terms can be paid slowly and never show up as paid late. If you want to know how long a customer will really take, its average time to pay and its standard terms tell you more than its late figure does. Both are in every company’s report.
Are big firms paying faster than they used to?
Yes, slowly. For periods ending in the first half of 2018, soon after reporting began, the typical company paid 27% of its invoices late and 54% within 30 days. By the first half of 2026, those were 15% and 64%.
Share of invoices paid within 30 daysShare of invoices paid later than agreed
Median of each company’s figures, by the half-year its reporting period ended, the first half of 2018 to the first half of 2026.
The typical average time to pay came down too, from 35 days to 31. None of it happened at once. The change came half a year at a time, with a setback in 2020.
Reports from 2025 onwards ask for some extra figures, such as the value of the invoices paid and the construction questions below. The three figures charted here have been asked the same way since the first report.
- 2018
- 35 days · 54% in 30 days · 27% late
- 2019
- 35 days · 55% in 30 days · 24% late
- 2020
- 34 days · 56% in 30 days · 24% late
- 2021
- 34 days · 59% in 30 days · 21% late
- 2022
- 33 days · 60% in 30 days · 20% late
- 2023
- 33 days · 62% in 30 days · 19% late
- 2024
- 32 days · 63% in 30 days · 17% late
- 2025
- 32 days · 64% in 30 days · 16% late
- 2026
- 31 days · 64% in 30 days · 15% late
Typical average time to pay, share paid within 30 days and share paid late. Every half-year is in the chart above.
Do companies with construction contracts pay differently?
Hardly. Of the 5,326 companies whose reports asked the question, 1,355 had construction contracts in the period. The typical one took 32 days to pay, paid 63% of its invoices within 30 days and 14% late. Every one of those is within two days or two points of the figure for all companies.
Two things to know before you lean on that. A construction contract here is any contract for construction work, so the list holds supermarkets, phone networks and water companies alongside the contractors and housebuilders. And the figures cover all of a company’s invoices, not only its construction ones.
So this is not how fast your main contractor pays its subcontractors. For that, look the company up: every report, with its standard terms written out, is in the government’s register, and every company’s latest figures are in our download.
If you are paid under the Construction Industry Scheme, what goes on the invoice is in the CIS invoice guide.
How many big companies hold back retentions?
Just over half of those with construction contracts: 751 of 1,355, or 55%, said their construction contracts include retention clauses. Where a company gave a standard rate, it was 5% in 248 cases out of 392, and 3% in 120.
A retention is a slice of each payment that the customer keeps back until the job is finished, and often until a defects period after it, as security for putting things right. On a £20,000 subcontract held at 5%, that is £1,000 you have earned and will wait months for.
Nobody had to say any of this before. The retention questions arrived for financial years starting on or after 1 April 2025, so the first answers are only now coming in.
- Companies with construction contracts
- 1,355
- With retention clauses
- 751 (55%)
- Stating a standard rate
- 392
- Of those, at 5%
- 248 (63%)
- Of those, at 3%
- 120 (31%)
- Releasing it in stages
- 574 (76%)
- Same terms as their own client
- 286 (38%)
As each company answered the register’s tick boxes. “Same terms” means the company says the retention it holds matches the one its own client holds on it.
Most of them, 76%, release the money in stages rather than all at once. Fewer than half, 38%, said they hold their suppliers to the same retention terms their own client holds them to.
What do these numbers mean for your invoices?
Expect a big customer to take about a month unless you agree otherwise, and agree it before the job. The average is counted from the day an invoice arrives, so the clock starts when you send it, not when you finish.
Three habits follow from that.
Invoice the day the job is done. Every day between finishing and sending is a day nobody is counting, least of all the customer.
Agree terms up front. A company’s standard terms are in its report. If they say 60 days and you cannot wait 60 days, the quote is the place to say so. What Net 14 and Net 30 mean, and the 30 day default when nothing was agreed, are in the payment terms guide.
Print the due date. “Due 20 October” is harder to miss than “Net 14”.
When a business does pay late, GOV.UK sets out statutory interest and a fixed sum you can claim; the payment terms guide has both. Whether to claim them from a particular customer is a question for whoever does your books.
How were these figures worked out?
From the government’s own register, downloaded on 8 October 2026, using each company’s latest report for a period that ended between 1 January 2026 and 30 June 2026. Every figure is a median of the companies’ own numbers.
The register held 115,384 reports. 6,020 companies reported for a period ending in the first half of 2026, and we left out 397 of them: reports that gave no figures, whose three payment bands did not add up to between 97% and 103%, or whose average was more than a year. Those are filing slips rather than slow payers.
We did not use the invoice values that newer reports include, because some are plainly in the wrong units. Every figure here is a number of days or a share of invoices, which the register records well.
Which companies have to report, and what each question means, is in the government’s guidance: in short, those over two of £54 million turnover, £27 million on the balance sheet and 250 staff.
The data, to download
payment-times-2026-h1.csv: 5,623 rows, one per company, with its average days to pay, the three payment bands, the share paid late, its standard terms, its construction and retention answers, and a link to its full report.
It is free to reuse. Contains public sector information licensed under the Open Government Licence v3.0. Source: Department for Business and Trade, payment practices reporting.
To cite this page: Invoice Koi, “Late payment statistics: how long big UK firms take to pay”, www.invoicekoi.com/uk/late-payment-statistics/, figures for the first half of 2026, downloaded 8 October 2026.
Asked about late payment
How long do big UK companies take to pay invoices?
About a month. In reports for periods ending in the first half of 2026, the typical large UK company took 31 days on average to pay an invoice and paid 64% of its invoices within 30 days.
What percentage of invoices are paid late in the UK?
Among large UK companies, the typical one paid 15% of its invoices later than agreed in the first half of 2026, down from 27% in the first half of 2018. Smaller companies do not have to report, so there is no matching figure for them.
What is a retention in construction?
Money a customer keeps back from each payment until the work is finished, and often until a defects period after it, as security for putting things right. Of large UK companies with construction contracts, 55% said they hold retentions, most often at 5%.
Which companies have to report their payment practices?
UK companies and LLPs that exceed two of three limits: £54 million turnover, £27 million on the balance sheet, and 250 employees. They report every six months, within 30 days of the period ending.
Where can I see how long a particular company takes to pay?
On the government’s payment practices register, by searching for the company’s name. Our download has every large company’s latest figures in one file, with a link to each full report.
Can I reuse these figures?
Yes. The download is free to reuse, with credit to the source: it contains public sector information licensed under the Open Government Licence v3.0.
Send it the day you finish.
The clock on a big customer starts when your invoice arrives. Invoice Koi writes it on the phone, on site, with the terms and due date printed; it needs no account, and sending needs a subscription, with a free trial where your store offers one.
On Google Play now. Coming soon to iPhone. Have the app? Open it
-
For electricians
-
For plumbers
-
For HVAC engineers
-
For builders
-
For carpenters
-
For roofers
-
For painters and decorators
-
For landscapers
-
For cleaning businesses
-
For handymen
-
For tilers
-
For flooring fitters
-
For plasterers
-
For mobile mechanics
-
For pest controllers
-
For appliance repair engineers
-
For garage door engineers
-
For locksmiths
-
For pool and hot tub engineers
-
For pressure washing contractors
-
For window cleaners
-
For carpet cleaners
-
For tree surgeons
-
For fencing contractors
-
For irrigation installers
-
For house clearance companies
-
For designers
-
For developers
-
For writers
-
For consultants
-
For photographers
-
For videographers
-
For event planners
-
For hairdressers
-
For tutors